A 20,000-litre rainwater harvesting tank constructed at Kashambya Health Centre III in Rukiga District remains unused after authorities refused to commission it over construction defects.
The tank was built in March 2026 by the International Crane Foundation (ICF), a non-governmental organisation that works with communities to protect wetlands and crested cranes.
The project was implemented under the Ministry of Water and Environment with funding from the United Nations Development Programme (UNDP) and the Green Climate Fund (GCF).
The tank was constructed at the staff residence occupied by the health centre in-charge to provide water for the in-charge and other health workers living nearby.
However, the tank has not been put to use after authorities reportedly discovered several defects, including leaking walls and floors, poorly installed gutters and missing tap stands.
Elineo Bandaganiire, the Kashambya Sub-county LCIII Chairperson, says authorities refused to commission the tank after discovering that it could not hold water.
He says the design of the structure also raised concerns about its durability, while the gutters meant to collect rainwater and direct it into the tank were poorly installed.
Bandaganiire says the contractor was instructed to fix the defects, but no repairs have been carried out. He, however, could not recall the name of the contracting company.
He compared the project to a similar rainwater harvesting tank built at Kantare Secondary School in the same sub-county, which was successfully commissioned after it was found to have no defects.
Joram Niwagaba, the district councillor representing Kashambya Sub-county, says the continued failure to use the tank is worrying because the health facility needs better infrastructure.
Niwagaba says district authorities had promised to intervene and ensure the defects were fixed, but no action has been taken.
Rukiga District LC V Chairperson Simon Mutebi says the district leadership is aware of the problem.
Mutebi says the original contractor hired another company to carry out the construction work. He adds that the district is waiting for the subcontractor to correct the defects before the tank can be commissioned.
However, Mutebi argues that the district should not be held responsible for the construction defects because it was not directly involved in implementing the project.